No.001 Preliminary investigation

Implementation period Every year
Standard Work Time 4.0H
Parts for Use and Replacement Complete set of check samples
Notes Perform a status check on the equipment.

No.002 Infrared Lamp Replacement

Implementation period Every year
Standard Work Time 0.5H
Parts for Use and Replacement Infrared lamp [1]
Notes The components used vary depending on the device specifications.

No.003 Replacement of the Fore-line Trap Element

Implementation period Every year
Standard Work Time 0.5H
Parts for Use and Replacement Element: 20-H026-00-050 [1 can]
Notes The components used vary depending on the device specifications.

No.004 Rotary Pump Oil Change

Implementation period every six months
Standard Work Time 2.0H
Parts for Use and Replacement Rotary Pump Oil
Notes The components used vary depending on the device specifications and manufacturer.

No.005 Heated Sample Stage Replacement

Implementation period Every year
Standard Work Time 2.0H
Parts for Use and Replacement Quartz stage, thermocouple, ICF gasket
Notes The components used vary depending on the device specifications.

No.006 Cleaning inside the heating chamber

Implementation period Implementation period
Standard Work Time 0.5H
Parts for Use and Replacement ICF gasket

No.007 Cleaning inside the load lock chamber

Implementation period Every two years
Standard Work Time 3.0H
Parts for Use and Replacement ICF gasket

No.008 Sample Transfer Mechanism Leaf Spring Replacement

Implementation period Every two years
Standard Work Time 1.0H
Parts for Use and Replacement Leaf spring, gasket

No.009 Infrared Guidance Mechanism Polishing

Implementation period Every two years (depending on the contamination status of the mechanical components)
Standard Work Time 1.0H
Parts for Use and Replacement Gasket

No.010 TMP(2)Bearing Replacement

Implementation period Every three years
Standard Work Time 3.0H
Parts for Use and Replacement Bearings, gaskets
Notes The components used vary depending on the device specifications.

No.011 Oil Mist Filter Replacement

Implementation period Every four years (depending on contamination levels)
Standard Work Time 0.5H
Parts for Use and Replacement Filter

No.012 Gate Valve Replacement

Implementation period Every four years
Standard Work Time 4.0H
Parts for Use and Replacement Gate valve, gasket
Notes Depends on the frequency of device usage.

No.013 Rotary Pump Replacement

Implementation period Every five years
Standard Work Time 2.0H
Parts for Use and Replacement Rotary pump, anti-vibration rubber

No.014 QMS Resolution and Mass Axis Adjustment

Implementation period Every year
Standard Work Time 2.0H
Parts for Use and Replacement Calibration Standard Gas

No.015 QMS Ion Source Replacement

Implementation period Every two years (depending on contamination levels)
Standard Work Time 2.0H
Parts for Use and Replacement Ion source, gasket

No.016 Vacuum Start-Up and Baking Set

Implementation period Every year
Standard Work Time 2.0H

No.017 Performance verification after overhaul

Implementation period Every year
Standard Work Time 5.0H
Parts for Use and Replacement Complete set of check samples
Notes Maintenance will always be performed.

No.018 Measurement for QMS Calibration Curves

Implementation period Every month
Standard Work Time 1.0H
Parts for Use and Replacement Ion-implanted wafer
Notes Perform after baking for at least one day.

No.019 Measurement for QMS Characteristic Correction

Implementation period Every year
Standard Work Time 3.0H
Parts for Use and Replacement Ion-implanted wafers (various types)